Skip to content

Dispute over new prison building has repercussions in court

The dispute over the construction of a new prison for Saxony and Thuringia in Zwickau has now reached the courts. Specifically, it is about access to all construction documents on a server. Following the termination of the contract with the general planner, there is a dispute over access to...

A barbed wire fence surrounds the grounds of a prison. Photo.aussiedlerbote.de
A barbed wire fence surrounds the grounds of a prison. Photo.aussiedlerbote.de

Penal system - Dispute over new prison building has repercussions in court

The dispute over the construction of a new prison for Saxony and Thuringia in Zwickau has now reached the courts. Specifically, it is about access to all construction documents on a server. Following the termination of the contract with the general planner, there is a dispute over access to this server, the Zwickau district court announced. The server was not operated by the general planner, but by a third company with which the state of Saxony, as the client, had no contract. It was therefore denied access. The state therefore took the matter to court.

In a provisional decision, a civil chamber ruled on Friday that the planner is not obliged to agree to the state taking over the project server. However, it must make the data available to the state via a new server. The existing contract with the server operating company may not be terminated until a legally binding decision has been made in the main proceedings. According to the court, the state has a claim to all documents created following the termination of the contract with the general planner.

The new XXL prison is to accommodate up to 820 prisoners from Saxony and Thuringia in future and replace old prisons. The first prisoners were originally due to move in as early as 2019. However, the project has been repeatedly delayed and the costs have skyrocketed. The state of Saxony announced in October that the contract with the general planner had been terminated, citing "increasingly inadequate service provision" as the reason. The company denied this and saw itself as a "pawn to cover up its own misconduct".

Due to the new disputes, the date for the opening of the prison is currently just as unclear as the exact costs. Most recently, there was talk of more than 300 million euros.

According to the information provided, both sides can appeal against Friday's ruling at the Dresden Higher Regional Court.

Read also:

  1. Despite the ongoing dispute in the courts over access to construction documents for the new prison in Zwickau, the epilogue of the project remains uncertain, affecting both Saxony and Thuringia's penal systems.
  2. In the midst of the dispute, justice for the general planner and the state of Saxony will be upheld as they appeal against the recent judgments made by the Zwickau district court and the Dresden Higher Regional Court.
  3. Despite the delays and escalating costs, the construction of the XXL prison in Zwickau remains a controversial issue within the broader context of Germany's penal system, affecting infrastructural processes and public trust in justice.
  4. The penal system in both Saxony and Thuringia has been impacted by the process of the construction of a new prison in Zwickau, highlighting the intricate relationships between justice, infrastructure, and politics.

Source: www.stern.de

Comments

Latest